Case Study

Reduced Lead Time and Cost Reduction by Over $15M

Chemical Processing Facility

Case Study

Fire
Soot
Water
Product Contamination

Services Provided

Subrogation
Technical Clerking
Inventory Analysis

The Situation

A major fire disrupted a critical chemical processing facility – destroying two buildings and damaging proprietary equipment. The client faced severe business interruption risk as one of only three global suppliers of materials essential to municipal water systems and other critical industries, including healthcare.

Equipment Impacted

  • Chemical Processing Machinery
  • Packaging Equipment
  • Shafts
  • Bearings
  • Controls
  • High-temperature Components

Value-Driven Solutions

Accelerated Production

Negotiated priority manufacturing with the OEM, cutting nickel pump casting lead time from 6-9 months to 2-3 weeks.

Fast-Tracked Repairs

Initiated large motor evaluations and rebuilds within days.

Innovation Over Obsolescence

Sourced alternatives for discontinued components.

Business Continuity

Enabled temporary operations and expedited critical-path repairs to limit interruption.

Fire at Chemical Processing Facility

The Results

Saved Time

Rapid recovery prevented extended shutdown.

Reduced Costs

$9.3M restoration cost vs. $24.6M – $31M RCV loss estimate.

Smart Asset Decisions

Strategic repair/ restoration preserved essential machinery.

Case Studies

Real Claims, Real Results

The Experts Behind the Best Outcome.